A fuel release from a tank can stop a sale or a loan. Buyers and lenders want a written result from the state. For many contaminated sites in Washington, that result comes from the Department of Ecology. For petroleum tank sites, it comes from a different agency. This guide explains the PLIA Technical Assistance Program and how a tank site gets a No Further Action opinion.
The short version
- The Pollution Liability Insurance Agency (PLIA) runs the Technical Assistance Program (TAP).
- TAP reviews your environmental reports and gives written opinions.
- A completed cleanup that meets the substantive requirements of the state cleanup law can get a No Further Action (NFA) opinion.
- PLIA lists an enrollment fee of $10,000 per release or tank system for gasoline and diesel sites.
- PLIA’s response goal for these sites is within 70 days of a request.
What the program is
PLIA is a Washington state agency. Ecology’s website says PLIA is a separate agency and is not an Ecology program.
PLIA says TAP assists underground storage tank owners and operators with advice and guidance on petroleum cleanups. PLIA reviews the environmental reports that you submit. Then it gives opinion letters. The letters are based on that review and on the state cleanup rule, chapter 173-340 WAC.
You still hire the consultant and the contractor. WAC 374-80-040 says the applicant may select an independent contractor to do the cleanup work. PLIA does not do the cleanup.
What PLIA can do under the rule
WAC 374-80-040 lists the services. PLIA may:
- Observe or interpret the results of a site investigation.
- Give technical assistance on how to meet the substantive requirements of the cleanup law.
- Review a planned cleanup and give a written opinion on whether more work is likely necessary.
- Review a completed cleanup and give a written opinion on whether more work is necessary.
- Give written opinions on request at each stage of the cleanup.
Who can use it
PLIA says it gives assistance to those with eligible gasoline or diesel underground storage tank systems. This is the path for a commercial site such as a gas station or a fleet yard.
WAC 374-80-040 sets three conditions. The applicant must show that:
- A release from an eligible petroleum storage tank system is suspected or confirmed at the site.
- The release has been reported to Ecology.
- The applicant is doing, or wants to do, an independent cleanup at the site.
The rule also says that an applicant with funding from certain PLIA programs is presumed eligible. One example is the underground storage tank loan and grant program.
The program also takes heating oil tank sites, with a different fee. Kee Enviro does not do heating oil tank work, so this guide does not cover those sites.
Report the release first
Enrollment does not replace the release report. A confirmed release from a regulated tank system must be reported to Ecology within 24 hours. The steps before that point are in our guide to underground storage tank closure in Washington.
What it costs
PLIA’s fee page lists these fees for gasoline and diesel sites.
| Fee | Amount | When it applies |
|---|---|---|
| Enrollment fee | $10,000 per release or tank system | Before the site is accepted into TAP |
| Periodic review fee | $2,500 per release or tank system | Only if the site needs a periodic review |
PLIA says a periodic review looks at site conditions and monitoring data after the cleanup. The aim is to make sure the site still protects human health and the environment.
WAC 374-80-050 adds three points about the fee:
- PLIA adjusts the enrollment fee each year in July. Check PLIA’s fee page before you budget.
- PLIA gives no advice or technical assistance until the fee is paid.
- The fee is nonrefundable, unless PLIA decides after enrollment that the tank system is not eligible.
PLIA also says that a site enrolled in another PLIA program may use the program funds to pay the enrollment fee.
These are agency fees only. Investigation, cleanup, and lab costs are separate. For those, read contaminated soil removal cost in Washington.
How to enroll, step by step
PLIA accepts applications online only.
- Get a Secure Access Washington (SAW) account. PLIA’s online community needs this account.
- Complete the application. An owner can apply for its own site. A consultant can apply on behalf of a client.
- Upload the reports. Put the relevant environmental reports in PLIA’s online folder.
- Schedule the intake meeting. PLIA requires this meeting for gasoline and diesel sites. You discuss the site with a PLIA site manager. You do not need to pay the fee to attend.
- Pay the enrollment fee. The fee must be paid before the site is accepted into TAP.
PLIA says an application is complete once the reports are uploaded and the intake meeting is scheduled. Enrollment follows the application review, the intake meeting, and the payment of the fee.
What to bring to the intake meeting
PLIA does not publish a checklist on its program page. These items are practical, and they help the discussion:
- The tank closure report and the site assessment report.
- Any Phase II report and lab data.
- A site map with the tank, piping, dispenser, and sample locations.
- Your goal and your date, such as a sale or a loan closing.
Response goals
PLIA says it aims to provide timely opinions. Its response goal is within 70 days of a request for gasoline and diesel sites.
That goal is for PLIA’s reply to a request. It is not the time for the full cleanup. The time to an NFA opinion depends on the site, the cleanup method, and the quality of the reports.
What a No Further Action opinion means
PLIA says it issues an NFA opinion for completed cleanups that meet the substantive requirements of the state cleanup law. PLIA also says an NFA may be helpful with property transfers.
Know the limits. WAC 374-80-010 says:
- An opinion under the program is advisory only.
- It is not binding on PLIA or on Ecology.
- Participation in the program is not a settlement with the state.
- Ecology may still require more cleanup if it finds that more is necessary.
PLIA may also rescind an opinion. WAC 374-80-040 allows this if PLIA learns that site conditions changed, or that the site no longer meets the requirements.
When a covenant is part of the cleanup
Some cleanups rely on an environmental covenant. WAC 374-80-045 says PLIA must then review the covenant at least once every five years. If the terms of the covenant are not followed, PLIA may rescind the NFA opinion.
TAP and Ecology’s Voluntary Cleanup Program
The two programs do a similar job for different sites.
| PLIA TAP | Ecology Standard VCP | |
|---|---|---|
| Agency | Pollution Liability Insurance Agency | Department of Ecology |
| Site type | Releases from eligible petroleum storage tank systems | Sites where the contaminant is not petroleum released from a petroleum storage tank system |
| Agency cost | $10,000 enrollment fee per release or tank system for gasoline and diesel sites | Free to apply, then an hourly rate billed monthly |
| Intake meeting | Required for gasoline and diesel sites | Free, on request |
| Result | Written opinions, and an NFA opinion for a completed cleanup | Written opinions, and an NFA opinion when the site meets all cleanup requirements |
Ecology’s page says dry cleaning, automotive repair, and spill sites are typically eligible for the VCP. It sends petroleum storage tank releases to PLIA. For the Ecology path, read the Voluntary Cleanup Program and No Further Action.
Some properties have both problems. An old gas station can also have a solvent release from a repair bay. Ask each agency which program takes which release before you apply.
How to keep the program moving
- Enroll with complete data. PLIA reviews what you submit.
- Do the sampling by the methods that PLIA accepts. WAC 374-80-040 says PLIA gives advice only when sampling and testing follow agency-approved methodology.
- Keep the site active. WAC 374-80-070 says PLIA may end a program agreement for reasons that include 12 consecutive months of inactivity at the site.
- Ask for a written opinion at each stage. Do not wait until the end.
One more rule helps enrolled sites. WAC 173-340-450 requires owners and operators to update the interim action report at least every three years after a confirmed release. That update is not required while the site is enrolled in a technical assistance program under chapter 374-80 WAC.
Next step
Kee Enviro plans investigations and cleanups for commercial petroleum tank sites and prepares the reports for agency review. See our remediation service and our UST removal and closure service. To talk through your site, contact us or call our Federal Way office at 206-914-4989.