A contaminated site can stall a sale, a loan, or a building permit. Washington’s Voluntary Cleanup Program (VCP) gives owners a clear path to fix it. At the end, Ecology can issue a No Further Action (NFA) opinion. This guide explains how the VCP works and what it costs to take part.
What the VCP is
The VCP is run by the Washington State Department of Ecology. It lets owners and developers clean up a site on their own, with Ecology review. You hire the consultant. You do the work. Ecology reviews your reports and gives written opinions.
Cleanups in the VCP follow the Model Toxics Control Act (MTCA) and its rules in WAC 173-340. Under MTCA, liability is strict, joint, and several. That is why many owners and buyers want a clear, written result.
What a No Further Action opinion does
An NFA opinion says that no further action is needed under state cleanup law. It is based on the information you submit. Ecology says its NFA opinions “normally provide lenders and other government agencies the information they need.”
For a buyer or lender, the NFA is often the goal of the whole cleanup. It turns an open question into a documented result.
Is your site eligible?
Ecology’s “Before you apply” page lists several conditions. A site may be eligible if:
- The contaminant is not petroleum released from a petroleum storage tank system.
- The contamination does not pose a significant or immediate risk to people or other living things.
- The site is not a landfill.
Ecology notes that dry cleaning, automotive repair, and spill sites are typically eligible.
Petroleum tank sites go to PLIA
Releases from petroleum storage tanks, such as gas station tanks, follow a different path. The Pollution Liability Insurance Agency (PLIA) runs a Technical Assistance Program (TAP). TAP gives site-specific advice and written opinion letters. PLIA is a separate agency, not part of Ecology.
PLIA lists a TAP enrollment fee of $10,000 for gasoline or diesel sites.
Standard VCP vs Expedited VCP
Ecology offers two tracks. The right one depends on your budget and your deadline.
| Standard VCP | Expedited VCP | |
|---|---|---|
| Application fee | None | $3,000, non-refundable |
| How Ecology is paid | Hourly staff time, billed monthly | $20,000 first prepayment, then $10,000 prepayments |
| Closeout fee | Not listed as a separate fee | $1,500, or $7,500 with periodic review |
| Review speed | No set target listed; Ecology notes slower replies in fall and winter | Opinion on the remedial investigation within 90 days |
| Best for | Owners without a hard deadline | Deals and projects with a fixed date |
Ecology also offers a free intake meeting. Use it to ask questions before you sign up.
Model remedy cleanups in the Standard VCP get extra help. Ecology says it gives up to two free reviews and opinions of documents after cleanup is done.
The VCP process step by step
- Investigate the site. A Phase II ESA or remedial investigation defines the contamination. See Phase I vs Phase II ESA.
- Request an intake meeting. It is free. Bring your data and questions.
- Apply and sign the billing agreement. For the Standard VCP, this is your agreement to pay for Ecology’s time.
- Submit your investigation report. Ecology reviews it and can give an opinion.
- Clean up the site. This may mean digging out soil, treating groundwater, or other methods.
- Submit the cleanup report. Include confirmation sample results.
- Receive the opinion. If the cleanup meets MTCA standards, Ecology can issue an NFA opinion.
When periodic review applies
Some cleanups leave contamination in place under a cap or with use limits. Those sites may need periodic review by Ecology. On the Expedited track, that raises the closeout fee from $1,500 to $7,500. Ecology reviews a site at least every five years when the cleanup relies on an environmental covenant or other institutional control.
Model remedies can save time
Ecology publishes MTCA model remedies for common site types. A model remedy is a preset cleanup approach. When a site fits one, the design and review may be simpler. Ecology’s NFA guidance page explains how model remedies tie to NFA opinions.
Ask your consultant early whether your site fits a model remedy.
Budgeting for a VCP cleanup
Ecology’s fees are only one part of the cost. Plan for these items as well.
| Cost item | Who sets it |
|---|---|
| Ecology oversight (Standard VCP) | Ecology hourly rate, billed monthly |
| Ecology fees (Expedited VCP) | Fixed fees and prepayments listed above |
| Consultant investigation and reports | Your consultant, quoted for each site |
| Cleanup work, such as excavation and disposal | Contractor and disposal site |
| Confirmation sampling and lab work | Consultant and lab |
For more on cleanup costs, read contaminated soil removal cost in Washington. For tank sites, see commercial UST removal and closure.
Tips to reach an NFA faster
- Define the contamination well before you dig. Gaps in data lead to more rounds of review.
- Pick the right track. If you have a closing date, compare the Expedited VCP costs to the cost of delay.
- Submit complete reports. Missing maps, tables, or lab data slow Ecology review.
- Plan around the season. Ecology says it gets more submissions in fall and winter.
Share the NFA with your deal team
Once you have the NFA opinion, send a copy to your lender, buyer, and attorney. Keep it with your Phase I and cleanup reports. A future buyer’s consultant will likely ask for it. If your cleanup left soil in place, also keep any use limits on file.
Next step