Enter the dates from your Phase I report and your closing date. See which parts are still inside the 180-day and one-year limits of the federal AAI rule.
The 180-day and one-year rules
The federal All Appropriate Inquiries rule, 40 CFR 312.20, sets two limits. The inquiry must be done within one year before acquisition. This tool counts the year from the oldest date you enter. Five parts must be done or updated within 180 days before acquisition: interviews, the lien search, the government records review, the site visit, and the Environmental Professional declaration.
Planning a closing? The due diligence timeline shows the latest date to order each report.
Frequently asked questions
How long is a Phase I ESA valid?
Under the federal AAI rule, the inquiry must be done within one year before you acquire the property. Five parts must be done or updated within 180 days before acquisition.
Which parts have the 180-day limit?
Interviews, the search for environmental liens, the review of government records, the site visit, and the Environmental Professional declaration.
Can a Phase I be updated?
Yes, if the report is less than one year old on the closing date. An update refreshes the parts that are older than 180 days. Ask Kee for a quote.
Does my lender use the same rule?
Many lenders follow the AAI dates. Some lenders set shorter limits. Check your loan terms.