Phase I and Phase II reports, property condition assessments, and seismic reviews for commercial loans in Washington and Oregon. Each report follows the standard your policy names.

What lenders need from us

01

A Phase I that meets AAI

ASTM E1527-21 is the Phase I standard. EPA recognizes it for All Appropriate Inquiries under 40 CFR Part 312.

02

Dates that are still valid at closing

The report must be done within one year before the purchase. Five parts must be done or updated within 180 days.

03

A clear next step when there is a REC

If the Phase I finds a recognized environmental condition, the report says so and says what a Phase II must test.

04

One firm for the building too

A property condition assessment follows ASTM E2018-24. A seismic review can be added for older buildings.

Two paths to your closing date.

A former gas station, from the day you order. One path if the soil is clean. One path if it is not, or if tanks are still in the ground.

Lane 1. No contamination found
Phase IPhase II
Ready to close about Week 10

Phase I, Phase II, then lender and attorney review.

Lane 2. Contamination found, or tanks still in the ground
Same as Lane 130-day noticeReports due 30 and 90 days after confirmation
Then cleanup and a PLIA review

30-day notice, tanks out, reports. Then cleanup and a PLIA review.

Washington deadlines on Lane 2

  1. About Week 8Notice of intent to Ecology, when the Phase II report arrivesWAC 173-360A-0810(1)
  2. 30 days after the noticeEarliest start of tank closureWAC 173-360A-0810(1)
  3. Within 24 hoursA confirmed release is reportedWAC 173-360A-0750(1)
  4. 30 days after a release is confirmedSite characterization dueWAC 173-340-450
  5. 30 days after closureChecklists and report dueWAC 173-360A-0810(2)(c)
  6. 90 days after a release is confirmedInterim action report dueWAC 173-340-450
  • Phase I, about 3 weeks
  • Phase II, about 5 weeks
  • Review, 1 to 2 weeks, or reports on Lane 2
  • Same as Lane 1
  • 30-day notice
  • Tanks out
Two paths from the day you order, in weeks. Report times are typical only. Rule deadlines are exact. Lane 2 assumes the notice goes to Ecology when the Phase II report arrives, and that a release is confirmed when the tanks come out. We confirm the dates in your quote.

How the work goes

  1. Send the address and the closing date

    We reply with a written quote and a delivery date.

  2. We do the records review and the site visit

    Many Phase I reports take two to three weeks, based on the site and the records.

  3. You get the report and a short summary

    The summary lists each finding and the recommended action.

  4. If a Phase II is needed, we scope it

    A focused Phase II often takes three to six weeks.

Services lenders use most

Free tools for lenders

Questions lenders ask

How long is a Phase I good for?

Under the federal All Appropriate Inquiries rule, the report must be done within one year before the purchase. Interviews, the lien search, the records review, the site visit, and the declaration must be done or updated within 180 days.

Can you update a Phase I from another firm?

Send us the report. We tell you if an update is possible or if a new report is the safer choice.

Which report does this loan need?

Use the free lender checklist. It shows which deals usually need a Phase I, a Phase II, a property condition assessment, or a seismic review.

We also work with

Tell us about your property.