For buyers and sellers

Know what is in the ground before you sign.

A Phase I before you buy protects your legal defenses. A Phase I before you sell lets you fix surprises before a buyer finds them.

What buyers and sellers need from us

01

Buyers: a Phase I before closing

Buyers need All Appropriate Inquiries for the CERCLA landowner defenses. A Phase I under ASTM E1527-21 meets that rule.

02

Buyers: time for a Phase II

If the Phase I finds a REC, a Phase II tests the soil, groundwater, or vapor. Plan for it in your feasibility period.

03

Sellers: no surprises in escrow

A report in hand lets you answer buyer questions early, or clean up before you list.

04

Both: plain answers

Each report says what was found, what it means for the deal, and what to do next.

Two paths to your closing date.

A former gas station, from the day you order. One path if the soil is clean. One path if it is not, or if tanks are still in the ground.

Lane 1. No contamination found
Phase IPhase II
Ready to close about Week 10

Phase I, Phase II, then lender and attorney review.

Lane 2. Contamination found, or tanks still in the ground
Same as Lane 130-day noticeReports due 30 and 90 days after confirmation
Then cleanup and a PLIA review

30-day notice, tanks out, reports. Then cleanup and a PLIA review.

Washington deadlines on Lane 2

  1. About Week 8Notice of intent to Ecology, when the Phase II report arrivesWAC 173-360A-0810(1)
  2. 30 days after the noticeEarliest start of tank closureWAC 173-360A-0810(1)
  3. Within 24 hoursA confirmed release is reportedWAC 173-360A-0750(1)
  4. 30 days after a release is confirmedSite characterization dueWAC 173-340-450
  5. 30 days after closureChecklists and report dueWAC 173-360A-0810(2)(c)
  6. 90 days after a release is confirmedInterim action report dueWAC 173-340-450
  • Phase I, about 3 weeks
  • Phase II, about 5 weeks
  • Review, 1 to 2 weeks, or reports on Lane 2
  • Same as Lane 1
  • 30-day notice
  • Tanks out
Two paths from the day you order, in weeks. Report times are typical only. Rule deadlines are exact. Lane 2 assumes the notice goes to Ecology when the Phase II report arrives, and that a release is confirmed when the tanks come out. We confirm the dates in your quote.

How the work goes

  1. Tell us the address and your dates

    We send a written quote after a short call.

  2. Phase I

    Records, a site visit, and a report. Many take two to three weeks.

  3. Phase II, if one is needed

    Targeted samples confirm or rule out each concern. A focused Phase II often takes three to six weeks.

  4. Cleanup path, if one is needed

    We lay out the cost, the schedule, and the right Washington or Oregon program.

Services buyers and sellers use most

Free tools for buyers and sellers

Questions buyers and sellers ask

Who pays for the Phase I, the buyer or the seller?

The buyer usually orders it, because the buyer needs the legal protection. The purchase agreement can set a different split.

What if the Phase I finds a problem?

A finding is not the end of a deal. A Phase II measures the problem. Then the parties can adjust the price, hold funds in escrow, or agree on a cleanup.

When must I order to meet my closing date?

Use the free due diligence timeline. Enter your closing date and it shows the latest date to order each report.